Investors

26
Jul

19 MW SUNfarming Solar Parks in Record Time

SUNfarming realized 5 more solar parks in the United Kingdom with a total capacity of 19 MW

In a record time of only 4 months SUNfarming has successfully completed 5 more solar parks, for 31th of March 2016, with a total capacity of 19 MW, including the transformers and grid connection. Despite adverse soil conditions and poor weather conditions 200 mechanics and engineers have done an excellent job.
As in 2015, the first cooperation with our English partner, Ethical Power LTD, this project was very professionally handled and implemented in time.
SUNfarming could for the majority deliver quality-tested SUNfarming solar modules. The substructures were delivered by our sister company SOLprime from Kiel that secured us the best SUNfarming quality and smooth handling.
Our solar parks are among the best on the UK's solar market. Together with investors and project developers, we are already working on the successful realization of new projects worldwide.

7
Apr

SUNfarming builds another 11 MW in Friedland

SUNfarming builds another 11 MW in Friedland

SUNfarming builds another 11 MW in Friedland, making it the largest producer of electricity in the region Friedland

11 megawatt solar park at three more locations in Friedland are since March 2016 connected to the grid.
As already several times in recent years, the trustful cooperation of SUNfarming with DKB also allowed the financing of these solar parks.Through our unique quality assurance system, we are a reliable partner for banks and investors.
"As production partners for our SUNfarming quality modules we chose Aleo Solar, producing in Prenzlau and Astronergy, producing in Frankfurt/Oder. Only economically strong PV module factories with automated production lines are added to the supply chain of SUNfarming.
Prior to delivery all modules are regularly tested at the factory by our SUNfarming quality managers, in collaboration with external testing institutes such as the PI Berlin, in a particularly strict quality control, "said Martin Tauschke, CEO of SUNfarming.
"We have successfully realized five solar parks with 22 MW, making SUNfarming the largest electricity producer in the region Friedland".

22
May

Intersolar Europe 2015

Intersolar Europe 2015, from June 10. – 12. 2015, booth B2.270
 
In 2013 SUNfarming's own plants achieved performance 5.3 % higher than forecast. In 2014 this rose to over 7.7 % additional performance.
 
Everyone ist talking about the energy transition, we are making it
You can see for yourself at our booth at the Intersolar, promised the SUNfarming team and management.
 

SUNfarming GmbH specialises in project development for capital investors and the realisation and active support of PV projects for commercial and private own electricity systems. With our experienced team of commercial staff, engineers and electrical engineers we have already successfully realised projects for 350 megawatts of capacity. Read more

2
Apr

Home Solar park investors SUNfarming has added 5 solar parks with a total capacity of 35 MW to the grid in the United Kingdom, within the deadline of 31/03/2015!

SUNfarming has added 5 solar parks with a total capacity of 35 MW to the grid in the United Kingdom, within the deadline of 31/03/2015!
 

Together with our British partner, Ethical Power ltd., we succeeded, in the record time of 4 months, in completing 5 solar parks, including transformers and grid connection, by 31/03 of this year. One of the solar parks was the largest SUNfarming project to date, with 12 MW of installed capacity. The park is situated in the south west of England, near Exeter.

The 6.5 MW Parkview project is a project developed wholly by SUNfarming UK. from the search for a site to grid requests and building approval. Read more